Cuba Street
Client – Weston Homes
Contract Value – £180k
Programme – 12 weeks
Principal contractor – Ivybuild
Works:
Site set / permits.
Erect scaffold.
Remove spandrel panels and existing insulation.
Install new rockwool to back of panel in accordance with specification.
Install horizontal and vertical cavity barrier insulation as per drawings received.
Weekly checks from building control for sign off.
All photographic evidence was taken and uploaded to Onetrace.